Client: Washington Suburban Sanitary Commission (WSSC)
Location: Potomac, Maryland
Services: Construction Management and Inspection
Completion Date: 2010
Keville Enterprises provided construction management and inspection services in connection with the $89M upgrade to the Potomac Water Filtration Plant in Potomac, MD.
Project elements included:
- New ultraviolet disinfection facilities
- New intermediate pumping station
- Improved rapid mix and flow split facilities
- Flocculation equipment upgrades
- Hydraulic improvements
- Electrical system enhancements
Keville served as the on-site representative for the WSSC and its CM-at-Risk contractor. Keville provided construction management, project controls and construction inspection services for the client.
Daily activities included: preparing daily progress reports; taking periodic construction progress photos and special field condition photos; verifying that all designated DBE subcontractors performed their portion of the work required by the contract; evaluating and processing proposed change orders; processing project submittals and providing weekly verification that the GC was maintaining a current set of as-built record drawings; reviewing the GC’s pay requisitions for accuracy and verifying that actual work had been completed; and ensuring that all daily reports, test results, and all additional reports, records, and documentation were maintained in a complete and orderly manner.